|
TO JEFF'S HOME PAGE TO JANE'S HOUSE |
CONTACT JEFF |
BUILDING SUAVESUEÑOS |
AUGUST 2009 |
|
This is what it looked like before we started.
|
We begin cutting our way down...
|
|
doing our best not to disturb the natural form...
|
and making sure the site is well-drained.
|
|
We make way for all the tubes...
|
|
|
and in they go... |
water, power, phone, black and gray water, rain drains.
|
SEPTEMBER 2009 |
|
We complete the roof on the carport...
|
the nursery... |
|
and the shop has a floor, too. At last a covered work space.
|
The original shed comes down.
|
OCTOBER 2009 |
|
The path gets graveled...
|
and the bank its rock wall... |
|
Excavation starts...
|
all by hand ~ too damaging to put a backhoe in here.
|
NOVEMBER 2009 |
|
The foot path gets tested by an authority in feet. These guys get big... this one's nearly six inches.
|
Nov. 6 Batter boards...
|
|
and strings (in holiday colors)...
|
foundation trenches.
|
|
The steel and roofing arrives...
|
|
|
the trenches grow.
|
All the tubes & wires...
|
|
in careful knots.
|
Where the old shed was.
|
|
The temporary power panel, some steel in the ground...
|
and the drain field is in.
|
DECEMBER 2009 |
|
We prepare to make another massive concrete mess...
|
and start pouring footings.
|
|
The footings are done.
|
We've passed inspection...
|
|
Materials (and their guardian) are standing by...
|
and we've got some foundation laid. |
|
Foundation work continues.
|
This is the library to come.
|
|
The foundations are almost all to floor level...
|
|
|
and the piers under the bedroom are set.
|
We stopped here for Christmas break.
|
JANUARY 2010 |
|
We're back at the shovels...
|
and the septic tank is in. |
|
After the storm (we had a 'bad winter' here too)...
|
we did a lot of pruning, and extended the drainage system.
|
|
The foundation block is at floor level...
|
and we've cut out the soft dirt (the first house-cleaning)...
|
|
and we begin making the base for the sub-floor.
|
Jan. 27 Rough plumbing.
|
|
More tubes...
|
and the gray-water system is complete.
|
FEBRUARY 2010 |
|
Conduit, breaker panel...
|
and we're hauling in the base-rock.
|
|
Jeff gets his own water-meter.
|
A leftover concrete panel from the street wall...
|
|
serves to protect the tank lids: "Like a bridge over troubled water" says Jane.
|
The terrace pier-bases are set.
|
|
Compacting the base rock...
|
it practically looks like a floor.
|
|
The path to the river grows.
|
The inspector approves.
|
|
We've hooked up the water...
|
and electricity. |
|
We start setting the beams for the bedroom floor...
|
the path is extended... |
|
and the base rock is all compacted.
|
We begin pouring the floor.
|
|
The bedroom floor frame goes in.
|
|
|
Caulking every nook...
|
and painting every cranny against the ever encroaching rust.
|
|
Stormy adds her signature.
|
Zairo & Isaías... mudmakers in the mist.
|
|
Mud on the bedroom floor.
|
More floor.
|
|
|
And more.
|
|
|
Closet floor and terrace frame.
|
|
The terrace is poured...
|
and the floor is complete.
|
MARCH 2010 |
|
Lonnie makes her mark.
|
Pudge, who officially lives next door, takes a siesta.
|
|
Up from the ground... the first wall blocks.
|
Another course of block...
|
|
|
And some more...
|
|
We use our concrete scrap to build the base of the path to the river.
|
More tubes and wires (the future site of water-heater, washer, dryer.)
|
|
Less imagination, if only a little less, is now needed to picture the shape of the house...
|
|
|
the pantry~laundry...
|
and the bath. Ok, it still takes a lot of imagination.
|
|
Now that we've reached this wall height...
|
we excavate the back entry.
|
|
using the beautiful topsoil in the garden...
|
which is looking much less like a construction site.
|
|
We install the 'Pata-Gallo" ground rods...
|
and the conduit and boxes for the kitchen counter.
|
|
Really taking on some height...
|
and some shape.
|
|
Almost to the wall tops on the north side...
|
|
|
Shadows in the back entry.
|
A very large grasshopper poses for a photo.
|
|
We set the steel for the bottom of the internal beam.
|
The last course in place, Zairo cuts the channel for the top of the beam.
|
|
We begin on the south side...
|
setting the first two courses of the closet...
|
APRIL 2010 |
|
and the library.
|
We move a little faster with the closet...
|
|
my block setting skills having improved...
|
if slightly.
|
|
We reach the top of the wall, the tallest of the house...
|
|
|
|
and the story-boards come down.
|
|
Starbright, our neighbor, observes...
|
and the Princess Topaz is a happy mom.
|
|
Now for the library walls...
|
|
|
We reach the top of the library wall, and pour the beam...
|
and start on the steel structure.
|
|
This is the central beam.
|
The kitchen gets a window sill.
|
|
The central beam is in place...
|
|
|
the center post arrives...
|
how long is it?
|
|
And by the end of the day...
|
the kitchen roof has rafters.
|
|
We begin the structure of the living room roof...
|
|
|
The Roof Pope gives his blessings...
|
as the upper roof grows.
|
|
|
Lately there's been an emergence of these large green cicadas. (Called chicharras around here...
the seam in the block he's sitting on is 2cm wide)
|
|
Nailers on the rafters of the kitchen...
|
|
|
and a beginning on the library roof.
|
Meanwhile back at the concrete...
|
MAY 2010 |
|
we've been working on the entrances.
|
The steel structure gets serious...
|
|
|
and the front entry is poured.
|
|
The bed and bath wing gets its rafters...
|
|
|
the library roof frame is complete...
|
and Stormy plays with the kittens.
|
|
Nailers on the bed and bath wing...
|
the roof is coming right along.
|
|
The rest of the rafters on the living room go up...
|
|
|
and the overall form of the house is finally revealed.
|
The complexity of the steel...
|
|
|
and if we put the ladder up from here...
|
|
we can work up in the treetops.
|
Another colorful neighbor.
|
|
Gallons and gallons...
|
of anti-corrosive primer...
|
|
to get the roof framing ready.
|
Some of the finish black while we have good access...
|
|
|
and...
|
|
window frames.
|
"Good access"...
|
|
isn't necessarily "easy access."
|
A little bird on my shoulder told me...
|
|
to get started on the roofing.
|
The bed and bath get the first panels.
|
|
In the morning, Jane comes to see the bedroom roof...
|
Chalo has finished framing the kitchen counter.
|
|
The living room roof is next...
|
and then the library...
|
|
and by the end of the day...
|
the house is roofed!
|
|
Over the next week, we work on windows...
|
|
|
and doors... |
and the first of the interior wall framing.
|
JUNE 2010 |
|
Now that the house has a roof, we work on gutters...
|
and clean the drain pipes.
|
|
Fulvio prepares the path in front of the library...
|
and Isaias transplants Bird of Paradise from the bath patio.
|
|
I do some more rockwork...
|
and more work with rock.
|
|
The interior framing continues...
|
and a fresh-water crab, who climbed in Jane's pantry window, ends up in the Tupperware.
|
|
Concrete culverts...
|
serve as collectors from the rain gutters.
|
|
|
The interior walls grow...
|
|
|
and the pila (laundry sink) is delivered (it's the wrong size, but we'll beat it to fit, and paint it to match.)
|
|
We set up shop in the living room...
|
and kitchen...
|
|
and get to work preparing the windows for glass.
|
|
JULY 2010 |
|
Every stop machined and numbered. I knew those hours spent with the Erector Set would pay off someday!
|
The tree ferns are happily pushing.
|
|
|
While waiting for the glass, we've put in some handles...
|
AUGUST 2010 |
|
and some latches...
|
and some wires.
|
|
Here comes the glass!
|
The next day...
|
|
|
the house is glassed in.
|
|
The front door gets some stained glass pieces...
|
and an etched piece that I've carried around for decades. |
|
The wild orchid that only lasts a day blooms in front of the terrace.
|
A Ranera (frog-eating tree snake) looks on from a tree.
|
|
Now that the glass is in...
|
we begin closing up the interior walls.
|
SEPTEMBER 2010 |
|
|
Some counter-tops go in the kitchen.
|
|
|
All this work is SO tiring!
|
|
Around 6:30 in the morning, the sun comes in like this. Delightful!
|
A visitor with remarkable feelers likes it too.
|
OCTOBER 2010 |
|
Stucco! |
|
|
And some lights.
|
We're not the only builders here.
|
NOVEMBER 2010 |
|
The terrace rail is complete.
|
|
|
The first tile is set...
|
|
|
and from there...
|
|
|
more follow. |
|
|
|
The details of the window frames look better with the walls closed up.
|
JANUARY ~ MARCH 2011 |
|
The tile saw threw a bearing just before Christmas... |
but we got the pila in while waiting for the parts...
|
|
and evenetually got the saw fixed...
|
|
|
|
and more tile set.
|
|
Terrace tiled...
|
the grouting begins.
|
APRIL 2011 |
|
The Scooter-Boot tries out the terrace...
|
I begin the mosaic in the living room.
|
|
|
We do some more rock work...
|
|
and build the sand garden...
|
just for fun.
|
MAY 2011 |
|
Finish tile in the shower... |
some finish painting, and a working toilet!
|